Saturday, July 30, 2011

July 23 2011

We had a smaller turnout this week again. 22 people including cooks and kitchen help


Worked on and completed:

  • The steps from the Main Lodge to the Outdoor Amphitheater were worked on. 1 group of 4 will be needed to complete these steps next Saturday.

  • Drilling and rebar was worked on on the girls side, additional steps will need to be completed on both the girls and boys side.

  • Pathway and stairs to the Cooks Cabin were completed.

  • Painters were finishing some of the trim painting on the doors. Electrical panel was worked on in the kitchen.

  • Clean up of construction debris was accomplished around the saunas and bathhouses, cleaned up the equipment room for the water filtration system and prepared for additional expansion as well.

  • Benches from the Upper Ramada were brought down to the seating area between the Main Lodge and the Staff Cabin.

  • Work continued on the girls side drain field with finishing some of the drain areas and digging for adding two additional drain lines.