December 13, 2008
Today was a foggy day with the high of 32 degrees. The Prescott guys built railings on 8 cabins, and also built twelve shutter windows for four cabins. The snow is coming so the work may be done for this season. There will be a board meeting on January 12, 2009 where plans and budget will be the main focus. Merry Christmas and Happy New Year to all.
December 6, 2008
A small crew from Phoenix and a new resident of Arizona, Gary Kesti from Flagstaff, spent the day at Kamp Kipa. They removed the tin roofs off two cabins and that tin was set aside as reusable material. The two cabins and one shed were demolished and all that material was put into the dumpster. The shower stalls were cleaned and all trash removed. That is it for December 6th with a small crew of about 7 or 8.