Started grading between the staff cabin and lodge
Built steps between staff cabin and lodge
Worked on areas around all cabins to finalize the pathways
Started removing brush and spread out dirt piles in all areas surrounding the cabins and pathways
Completed electrical work in staff cabin; it is now ready to trim
Backfilled the second drain pipe from one of the septic tanks to the drain field to protect the pipes
Completed and painted the exteriors of the lodge, staff cabin and men’s and women’s bathrooms
Cleaned, stained and final-coat sealed kitchen floor and handicapped bedrooms
Continued to move dirt to build up the gathering area adjacent to the patio off the lodge
Removed trees and brush in parking area by caretaker’s cabin
Dug footings for new saunas, they are ready for concrete
Final grading and trenching of drain fields for drainpipe
More pictures from Saturday:
Caretaker's cabin
Looking down at Kamp from the upper road
Upper ramada
The kids who will soon be attending the camp are a big help
Listed below are the landscaping and constructions projects that we will continue to work on or begin doing:
Landscaping
Complete the pathways, landscaping, and retaining walls
Grade parking area by caretaker’s cabin
Cleanup landscape/remove brush – brush will not be burned until the monsoon rains begin
Build additional pathways and steps
Cut rebar, drill steps, and install rebar on steps
Place and line all pathways/steps with rocks and boulders
Final grade between lodge and staff cabin
Dig trenches for septic system
Install and pack AB
Build retaining wall with large boulders for additional area by patio
Cut trees and stage for burn or people to pick up
Construction
Permits secured to add on saunas to bathrooms so that work will begin
Complete installation and drywall in kitchen
Install kitchen hoods
Paint interior of lodge and kitchen
Clean, stain, and finish lodge floor
Trim staff cabin
Additional plumbing adjustments are needed based on inspections
Clean, stain and seal exteriors of all sleeping cabins