The largest group so far!


With the help of a backhoe, steps are built from driveway to main lodge



Completing the job



New framework in staff cabin



Extinguishing one of five brush fires

Work completed in:

Main Lodge:
Underground plumbing set in place
All floor sinks in
All 1x2 slats removed from siding

Girls Bathroom:
Replaced rotted exterior sill plate
Framed all interior walls
Marked floor for new toilet drains
Removed damaged siding and 1x2 slats

Boys Bathroom:
Removed 1x2 slats
Marked where new walls will be constructed
Marked floor for new toilet drains
Removed concrete around existing toilet drains

Staff Cabin:
Poured slab for exterior stairs
Installed new deck railing
Straightened existing exterior walls
Framed interior walls

Septic:
Installed new lines from both girls bathroom and lodge to drain field

Excavation:
Back filled south end of lodge and water/sewer lines