Monday, August 30 through Saturday, September 4 is Kamp Kipa Work Week. There will be work for anyone who can show up any day of the week. There will be lunch/dinner served Friday and breakfast/lunch served Saturday. The following list is a tentative plan for the week:
Main Lodge:
- Install new soffit for eaves and overhangs
- Install new windows
- Install new siding and trim
- Work on new rough plumbing in kitchen
- Finish framing interior walls
- Install new exterior doors
Cabins:
- Connect final electrical so there is electricity available to all cabins.
Excavation:
- Install new grease tank
- Cover all underground power
Staff Cabin:
- Run new electrical wires
- Install new windows
- Install new soffit for eaves and overhangs
- Install new siding and trim
- Install new exterior door
Bathrooms:
- Run new electrical wires
- Frame new exterior water heater closet and roof
- Install new windows
- Install new soffit for eaves and overhangs
- Install new siding and trim
- Install new exterior doors
We hope to have a busy and successful week!
Saturday, August 28, 2010
Tuesday, August 24, 2010
August 14
Saturday the 14th had another large turnout of help. The cabins' windows and shutters were stained and electrical work to the cabins continued. In the lodge a meeting room was framed and the kitchen floored was raised 8" to match the rest of the building's floor. Prep work for the lodge patio continued and it should be ready for concrete soon. Some of the trenches with new electrical conduit were backfilled.
Wednesday, August 11, 2010
August 7
A rainy day
West wall in lodge
West wall in lodge
Kitchen trenches filled in
Staff cabin steps complete
Staff cabin deck
Staff cabin ready for plumbing and electrical
Girl's bathroom plumbing
Girl's bathroom
Boy's bathroom
Boy's bathroom
Septic by boy's bathroom complete
Still burning brush
Despite another rainy day, Kamp Kipa saw another large workforce last Saturday. Eleven tradesmen from Colorado traveled down Friday to work on plumbing. They completed the rough-in plumbing in both the girl's and boy's bathrooms and started the staff cabin plumbing. Much more was accomplished Saturday; half of the lodge has been framed, the lower patio is being prepped, the patio and kitchen have been backfilled, and some of the electricity has been run to cabins. Running the electricity includes digging trenches and running conduit and wire. We are so thankful for all of the willing workers and the many accomplished tasks at Kamp. God has blessed our work and we pray for continued blessings.
Thursday, August 5, 2010
Last Week of July
The lodge from above
Cabins and lodge
Inside the lodge, view from the kitchen
Visitors
Framing in staff cabin
Staff cabin deck
Staff cabin steps
Prepping grease trap
Looking down at drain field and recreation area
Burning brush
Assessing electrical needs
A break from the rain
Even amid the rain, 15 adults and several children worked cheerfully last Saturday.
Work accomplished:
Staff Cabin:
Added 2nd top plate to interior walls
Plumbed up interior walls and door openings
Installed drywall backing for walls and ceiling
Constructed new entry stairs and railings
Removed door plates
Installed H2.5s on trusses
Added missing 2x8 ceiling joist
Girls Bathroom:
Replaced some exterior siding as needed with 3/8" OSB
Installed H2.5s on trusses
Boys Bathroom:
Moved dirt/concrete debris to outside
Framed all interior walls
Installed H2.5s on trusses
Excavation:
Dug new electrical underground ditches from Lower cabins to Boys Bath
Determined where power supply will run from Bathrooms to Cabins
Saturday July 24
The largest group so far!
With the help of a backhoe, steps are built from driveway to main lodge
Completing the job
New framework in staff cabin
Extinguishing one of five brush fires
Work completed in:
Main Lodge:
Underground plumbing set in place
All floor sinks in
All 1x2 slats removed from siding
Girls Bathroom:
Replaced rotted exterior sill plate
Framed all interior walls
Marked floor for new toilet drains
Removed damaged siding and 1x2 slats
Boys Bathroom:
Removed 1x2 slats
Marked where new walls will be constructed
Marked floor for new toilet drains
Removed concrete around existing toilet drains
Staff Cabin:
Poured slab for exterior stairs
Installed new deck railing
Straightened existing exterior walls
Framed interior walls
Septic:
Installed new lines from both girls bathroom and lodge to drain field
Excavation:
Back filled south end of lodge and water/sewer lines