Tuesday, July 5, 2011
June 25 2011
Once again we had a great turnout with approximately 60 workers! The Kamp is really starting to look finished and progress is becoming more and more evident. Thank you to all who have helped in any way. If the energy can continue all summer, we will be ready for camps before the snowfall.
Lodge:
- The exterior is completely painted and some of the exterior lighting has been installed.
- The kitchen and ADA portions are being sheet-rocked this week.
- The next step for the Lodge/Kitchen is to install FRP on some of the walls to prevent moisture/mold build up around areas with water use. Then it's painting and equipment installation!
Baths:
- The saunas are partially framed and could possibly be completed this weekend (framing portion)
- The slabs will be poured once the framing is done
- The showers have curbs and a sloped floor
- The next step for the baths is to complete framing of saunas and install the siding, trim and windows
Staff Cabin:
- We passed our final inspection with a few items left to finalize. Otherwise it's done!
Septic System:
- Progress continues and both leach fields have been dug and some pipe installed on the Men's side.