Monday, October 11, 2010
First Week of October
Three patios on the main lodge are prepped and ready for concrete. They will be poured soon if the weather cooperates. The rough electrical in the sanctuary is 90% complete. The roof over the sanctuary is complete except for a ridge cap and roof jacks. The kitchen roof cannot be completed until spring when the walk-in freezer is expected to be installed.
The girl's bath house has new siding on three of four walls and the boy's bath is ready for siding. A leak under the boy's bath house has been detected and repaired.
Both baths have been approved for the Rough Combo inspection. This included framing, plumbing, electrical. Both houses will soon be ready for insulation and drywall.
The staff cabin has also passed the Rough Combo inspection and is ready for insulation and drywall.