Worked on and completed this week:
Completed backfill of girl's side drain field
Completed rough grade for the camp storage units
Removed three large trees that needed to be dropped for safety purposes
Cut area from hillside south of the girl's side drainfield to prepare a pad for a basketball court
Girl's sauna and bathhouse roof was worked on
Several crews hauled brush from the cabin areas to burn
Up to 20 guys gathered and placed rock on the hillside west of the lodge
Two chain saw crews cut down logs and brush throughout the camp to movable lengths for burning and removal
Completed interior sheeting and paint in the water treatment room, it is ready for equipment to be installed
The drain lines were finished and tied into the collection box and were backfilled
Installed two septic tanks by the girl's bathroom, they need to be adjusted for height, leveled and backfilled
Five electricians worked throughout the camp. We were able to get a majority of the electrical completed:
Exterior lights on lodge and bathhouse
Kitchen is almost complete
Finished wiring for refrigerator and freezer, both are working as expected
Continued work on the west side retaining wall and extended patio. 8-12 guys worked on this throughout the day making it 80% complete
Electricians in kitchen
Rory S installing exterior light on lodge
Man and machine working together
Work on the west side
More work on west side, along path leading to future amphitheater
West side of lodge
Very big holding tanks
Stihls at a stand-still
Felling trees
Clearing
Burning
Girl's side drain field
More on girl's side
Working on bathhouse roof
On bathhouse roof
Spraying polyurea coating in bathhouse
Doesn't this look nice?