Wednesday, September 29, 2010
September
Cabin
Ramada
Staff Cabin
Main Lodge, view of kitchen
Steps in progress
Volunteers in lunch line
A very large group of volunteers came to help our guys
Any help is welcome!
The most noticeable project in September has been the new steps running through kamp. A group of 45 volunteers from the community worked on new paths from cabins to ramadas and bath houses. There will be lighting added to the paths in the future.
The next phases for the staff cabin will be insulation and drywall.
The lodge now has new windows, exterior doors and siding. Rough plumbing is complete and the kitchen roof is projected to be finished by the end of September. HVAC and electricity should be complete by mid-October.
The bath houses have new windows, exterior doors, electrical and interior framing. They are ready for siding, which is planned for October.
Monday, September 6, 2010
A Great Work Week!
Saturday morning breakfast
Cooks preparing a "mountain man" breakfast
Beginning steps from boy's bathroom to boy's cabins
The steps crew on Friday
Finished product
Finished product
Backhoe always busy
Siding the staff cabin
Wiring in staff cabin
Laying metal roofing
Lodge roof
Lodge meeting room
Lodge kitchen
Plumbing in kitchen
Saturday lunch break
A view of Kamp after a busy week
A summary of the full week's accomplishments:
Main Lodge:
- The exterior walls have the new underlayment on as well as shims to correct the wandering studs. The east side of the lodge is now straight and has window/corner trim on in prep for siding. Siding is ready to be installed on the east side
- Exterior eaves and overhangs have new soffit and venting.
- The new metal roof over the sanctuary portion has been completed.
- HVAC contractor is plugging away at the new system.
- Rough plumbing is in the kitchen and handicap portions. Not 100% complete.
- Underground conduit for electricity to Staff Cabin was installed from Electrical panel on West side to the SW corner
- Installed new grease tank on NW corner
Cabins:
- Completed connection from underground power to all cabins. All cabins have lights and electricity at the outlets
- Cleaned and vacuumed some cabins
- Put the Stony Lake donated mattresses in three of the cabins
Staff Cabin:
- New lap siding, windows, trim, soffits and soffit venting are complete. Exterior is complete with exception to the deck cover, gable vents and metal roof.
- Electrical layout completed. This includes some of the outlets, switches and fixture boxes
Ramada's:
- Installed new lights and outlets in all 5 ramada's
Landscaping:
- There has been a drastic improvement in this area. A large group of workers completed new stairs from the boys bath to the cabins and connected cabins on the boys side (West).
- General cleanup of the grounds performed by youth and children.
- Burned some slash and wood scrap piles
Excavation:
- Continuous
Upper bathhouse:
- Installed new water heater elements