Tuesday, May 10, 2011

Kamp Kipa Construction Resumes

After a bit of unexpected snow in April, work at Kamp has begun again. We look forward to another busy summer as we prepare to open the camp.

Tasks completed since work resumed May 1st:

Caretakers Cabin:

A. Completed tasks:
1. Fixed a few leaks found in water system - water is on
2. Thoroughly cleaned and touch-up painting completed
3. Removed worn out furniture and replaced with gently used items


B. Tasks needing to be done:
Outside cleanup of slash/logs/brush

Main Lodge:

A. Completed Tasks:
1. Office doors and trim installed
2. Rough electrical in kitchen
3. Rough plumbing in kitchen ready for rough combo inspection
4. Fireplace hearth repaired
5. Kitchen hood system ducts and holding brackets installed and ready for inspection (hood has arrived on site)
6. 1x6 T&G pre-stained
7. Roofing trim work
8. Steps and landing for patio on West side are formed and awaiting concrete

B. Tasks needing to be completed:
1. Install 1x6 T&G on Sanctuary ceiling
2. Finish rough electrical in kitchen
3. Rough Combo Inspection

Staff Cabin:

A. Completed Tasks:
1. Interior doors and trim installed

B. Tasks needing to be completed:
1. Caulking and painting of interior walls and doors

Baths:

A. Completed Tasks:
1. Installed plywood backing in prep for Vortex spray on walls
2. Submitted revised prints to Yavapai County for updated permit (this is for sauna addition)

B. Tasks to be completed:
1. Obtain updated permit

Cabins:

B. Tasks to be completed:
1. Pressure wash exterior to prep for finishing (oil)

Groundskeeping:

A. Competed tasks:
1. Brush and unusable fire wood burned

B. Tasks to be completed:
1. Continue burning brush and unusable wood
2. Clean/Rake entire area and burn prior to May 18th (PNF burn restrictions will be activated)



Excavation:

Tasks to be completed and currently under review:
1. Plan/prep for final grades/parking

Water System:

A. Tasks completed:
1. Rough pad leveled for new water tanks
2. Water turned on and available throughout
3. Fixed minor leaks at upper bath and well

B. Tasks needing to be completed:
1. Pour concrete for new water tanks
2. Filtration system

Septic System:

B. Tasks needing to be completed:
1. Submit permit